TAR_1708 — Hydroprocessing Turnaround Shutdown · Schedule % Complete by phase
SPI 1.00CPI 1.10
A.1Isolation & Prep
100%
A.2Decoupling & Removal
49.3%
A.3Inspection & Repairs
5.6%
A.4Reassembly & Box-Up
14.5%
A.5Testing & Start-Up
5.2%
01 — Profile

Professional Summary

Electronics and Communication Engineering graduate with hands-on training in project planning and scheduling using Primavera P6, gained through a certification-based internship covering scheduling, resource allocation, cost control and progress monitoring. Comfortable with WBS development, critical path analysis and Earned Value Analysis (CPI, SPI, CV, SV). Seeking an entry-level Planning Engineer role to apply these skills to live construction, infrastructure or industrial projects.

Primavera P6 MS Project WBS Development Critical Path Analysis Resource Allocation Cost Control Earned Value (CPI/SPI) S-Curves & Dashboards Power BI Excel

B.E. — Electronics & Communication Engineering

PA College of Engineering, Mangalore
Dec 2021 – Jun 2025

Primavera P6 Project Management Certification

Synergy School of Business Skills, Mangalore
20 Jun 2026 – 06 Jul 2026

Project Management Trainee

Synergy School of Business Skills, Mangalore
Jun 2026 – Aug 2026
02 — Case Study

Hydroprocessing Turnaround Shutdown

A Primavera P6 planning exercise developing and monitoring a full turnaround schedule: WBS, activity network, resource and cost loading, and earned-value tracking across five execution phases from isolation through start-up. Project start milestone: 17-Aug-2026.
Training / case-study project completed under faculty guidance at Synergy — not prior industrial employment.

A.1Isolation & Prep — plant shutdown, LOTO, scaffolding, logistics4.75d actual · 100% complete
A.2Decoupling & Removal — unbolting, pipe spool & bundle extraction, vessel opening2.71d actual / 3.71d remaining
A.3Inspection & Repairs — hydro-blasting, NDT/QAQC, rotating & E&I maintenance1.96d actual / 6.71d remaining
A.4Reassembly & Box-Up — box-up, piping reassembly & de-blinding, scaffold strike0.96d actual / 8.96d remaining
A.5Testing & Start-Up — leak tests, loop checks, demobilization & handover0.79d actual / 10.00d remaining
1.10
Cost Performance Index
1.00
Schedule Performance Index
₹6.9Cr
Budget at Completion
24.8%
Overall % Complete
IDActivityDurationStatusCPI
A1001Mechanical Line Blinding2.00dComplete1.05
A1009Erect Scaffolding – Zone C3.00dComplete1.04
A1024Motor/Pump Decoupling (P-102)0.50d / 1.50d rem.25%1.14
A1045Hydro-blasting of Exchanger Tubes2.50d / 0.50d rem.83.3%1.06
A1097De-blinding Piping System – Zone A1.70dComplete1.06
A1071Fresh Catalyst Loading R-1013.00d rem.Not started
A1119Plant Ready for Start-Up Sign-Off1.00d rem.Not started

Scheduling & Planning

  • WBS development across 5 execution phases
  • Activity network for mechanical, E&I, inspection & testing scopes
  • Milestone definition (start / finish of project)

Progress & Cost Control

  • Actual vs. remaining duration tracking
  • Cost & schedule performance indices (CPI, SPI)
  • Budget at completion & variance monitoring

Reporting

  • Gantt-chart activity communication
  • Earned-value S-curve reporting
  • Activity & performance report generation
03 — Experience

Training & Internship

Jun 2026 – Aug 2026

Project Management Trainee

Synergy School of Business Skills, Mangalore, Karnataka
  • Prepared a baseline schedule and turnaround plan in Primavera P6 under faculty guidance as part of the training curriculum.
  • Completed hands-on certification training covering project scheduling, resource allocation, cost control and WBS development.
  • Allocated resources and monitored cost control measures to keep the turnaround plan aligned with budget and manpower constraints.
  • Delivered progress dashboards and S-curve reports in Primavera P6 to communicate schedule status to stakeholders.
Dec 2021 – Jun 2025

B.E., Electronics & Communication Engineering

PA College of Engineering, Mangalore
  • Engineering foundation in systems thinking, technical documentation and structured problem-solving, now applied to planning and scheduling work.
04 — Contact

Let's Talk Scheduling

Open to Planning Engineer Trainee, Junior Planning Engineer, Project Controls Trainee and Shutdown/Turnaround Planning Trainee roles.